🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Indiana

GAS · MISO

Gas project J3999, Vermillion County

Gas project J3999, Vermillion County is a 1,540 MW gas request in interconnection study in the MISO interconnection queue, in Vermillion County, Indiana, connecting to DUKE ENERGY INDIANA.

Queue statusIn planning
  1. PlanningQueued Apr 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3999
Grid region
MISO (Midcontinent)
Utility / transmission owner
DUKE ENERGY INDIANA
Connection point (POI)
Sugar Creek - Cayuga CT 345.0kV
Location
Vermillion County, Indiana
Technology
Gas: 1,540 MW
Total requested
1,540 MW
Service type
Network resource (NRIS)
Queue status
Active
Entered queue
14 April 2025
Proposed online date
January 2030

Location

Marker shows the centre of Vermillion County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Vermillion County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem