🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Indiana

ONSHORE WIND · MISO

Onshore wind project J4063, Knox County

Onshore wind project J4063, Knox County is a 300 MW onshore wind request in interconnection study in the MISO interconnection queue, in Knox County, Indiana, connecting to DUKE ENERGY INDIANA.

Queue statusIn planning
  1. PlanningQueued Sep 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J4063
Grid region
MISO (Midcontinent)
Utility / transmission owner
DUKE ENERGY INDIANA
Connection point (POI)
Gibson Sta - Bedford 345 345.0kV
Location
Knox County, Indiana
Technology
Wind: 300 MW
Total requested
300 MW
Service type
Network resource (NRIS)
Queue status
Active
Entered queue
4 September 2025
Proposed online date
August 2030

Location

Marker shows the centre of Knox County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Knox County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem