United States › Grid › Interconnection queues › Indiana
SOLAR · MISOSolar project J3731, Knox County
Solar project J3731, Knox County is a 160 MW solar request in interconnection study in the MISO interconnection queue, in Knox County, Indiana, connecting to DUKE ENERGY INDIANA.
Queue statusIn planning
- PlanningQueued Apr 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jan 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3731
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- DUKE ENERGY INDIANA
- Connection point (POI)
- Edwardsport - Vincennes 138.0kV
- Location
- Knox County, Indiana
- Technology
- Solar: 160 MW
- Total requested
- 160 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Active
- Entered queue
- 17 April 2024
- Proposed online date
- January 2027
Location
Marker shows the centre of Knox County; the queue data does not give exact sites.
Other requests in Knox County
- Solar project J1234, Knox CountySolar · 100 MW · agreement signed
- Solar project J1235, Knox CountySolar · 50.0 MW · agreement signed
- Onshore wind project J4063, Knox CountyOnshore wind · 300 MW · in study
- Solar project J1616, Knox CountySolar · 200 MW · in study
- Solar + storage project S1120, Knox CountySolar + storage · 150 MW · in study
- Battery storage project J3166, Knox CountyBattery storage · 100 MW · in study
- Solar project J3896, Knox CountySolar · 70.0 MW · in study
- Solar project J3925, Knox CountySolar · 70.0 MW · in study
- Solar project J3897, Knox CountySolar · 60.0 MW · in study
- Battery storage project S1126, Knox CountyBattery storage · 50.0 MW · in study
- Gas project G431, Knox CountyGas · 420 MW · built
- Coal project G675, Knox CountyCoal · 200 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem