Solar project J1234, Knox County

Solar project J1234, Knox County is a 100 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Knox County, Indiana, connecting to DUKE ENERGY INDIANA.

Queue statusConsented
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedFeb 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2023 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1234
Grid region
MISO (Midcontinent)
Utility / transmission owner
DUKE ENERGY INDIANA
Connection point (POI)
Edwardsport - Washington Mun, Linton 138kV Line
Location
Knox County, Indiana
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Active
Entered queue
29 April 2019
Agreement signed
10 February 2025
Proposed online date
September 2023

Location

Marker shows the centre of Knox County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Knox County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem