SOLAR · MISOSolar project J3931, Jasper County
Solar project J3931, Jasper County is a 500 MW solar request in interconnection study in the MISO interconnection queue, in Jasper County, Indiana, connecting to NORTHERN INDIANA PUBLIC SERVICE COMPANY.
- PlanningQueued Feb 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2030 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3931
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- NORTHERN INDIANA PUBLIC SERVICE COMPANY
- Connection point (POI)
- Other_
- Location
- Jasper County, Indiana
- Technology
- Solar: 500 MW
- Total requested
- 500 MW
- Service type
- Network resource (NRIS)
- Queue status
- Active
- Entered queue
- 7 February 2025
- Proposed online date
- September 2030
Location
Marker shows the centre of Jasper County; the queue data does not give exact sites.
Other requests in Jasper County
- Solar project J1067, Jasper CountySolar · 240 MW · under construction
- Onshore wind project J1069, Jasper CountyOnshore wind · 200 MW · under construction
- Solar project J847, Jasper CountySolar · 90.0 MW · under construction
- Solar + storage project J1340, Jasper CountySolar + storage · 200 MW · agreement signed
- Solar + storage project J1336, Jasper CountySolar + storage · 200 MW · agreement signed
- Solar + storage project J1339, Jasper CountySolar + storage · 200 MW · agreement signed
- Solar project J643, Jasper CountySolar · 175 MW · agreement signed
- Solar project J1387, Jasper CountySolar · 60.0 MW · agreement signed
- Schahfer CCGTsGas · 2,740 MW · in study
- Replacing 722 MW Coal with 285 MW of Battery and 437MW of Gas; SchahferGas · 733 MW · in study
- Onshore wind project J968, Jasper CountyOnshore wind · 200 MW · built
- Solar + storage project J1335, Jasper CountySolar + storage · 200 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem