Onshore wind project J968, Jasper County

Onshore wind project J968, Jasper County is a 200 MW onshore wind request built and operating in the MISO interconnection queue, in Jasper County, Indiana, connecting to NORTHERN INDIANA PUBLIC SERVICE COMPANY.

Queue statusOperating
  1. PlanningQueued Mar 2018 (completed)
  2. ConsentedOct 2021 (completed)
  3. Construction (completed)
  4. OperatingApr 2023 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J968
Grid region
MISO (Midcontinent)
Utility / transmission owner
NORTHERN INDIANA PUBLIC SERVICE COMPANY
Connection point (POI)
Reynolds 345kV Substation
Location
Jasper County, Indiana
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: In Service
Queue status
Operational
Entered queue
12 March 2018
Agreement signed
12 October 2021
Proposed online date
April 2023
Came online
April 2023

Location

Marker shows the centre of Jasper County; the queue data does not give exact sites.