ONSHORE WIND · MISOOnshore wind project J1069, Jasper County
Onshore wind project J1069, Jasper County is a 200 MW onshore wind request under construction in the MISO interconnection queue, in Jasper County, Indiana, connecting to NORTHERN INDIANA PUBLIC SERVICE COMPANY.
Queue statusUnder construction
- PlanningQueued Mar 2018 (completed)
- ConsentedOct 2021 (completed)
- Construction (current stage)
- OperatingTarget Apr 2023 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1069
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- NORTHERN INDIANA PUBLIC SERVICE COMPANY
- Connection point (POI)
- Reynolds 345kV Substation
- Location
- Jasper County, Indiana
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Under Construction
- Queue status
- Active
- Entered queue
- 12 March 2018
- Agreement signed
- 12 October 2021
- Proposed online date
- April 2023
Location
Marker shows the centre of Jasper County; the queue data does not give exact sites.
Other requests in Jasper County
- Solar project J1067, Jasper CountySolar · 240 MW · under construction
- Solar project J847, Jasper CountySolar · 90.0 MW · under construction
- Solar + storage project J1340, Jasper CountySolar + storage · 200 MW · agreement signed
- Solar + storage project J1336, Jasper CountySolar + storage · 200 MW · agreement signed
- Solar + storage project J1339, Jasper CountySolar + storage · 200 MW · agreement signed
- Solar project J643, Jasper CountySolar · 175 MW · agreement signed
- Solar project J1387, Jasper CountySolar · 60.0 MW · agreement signed
- Schahfer CCGTsGas · 2,740 MW · in study
- Replacing 722 MW Coal with 285 MW of Battery and 437MW of Gas; SchahferGas · 733 MW · in study
- Solar project J3931, Jasper CountySolar · 500 MW · in study
- Onshore wind project J968, Jasper CountyOnshore wind · 200 MW · built
- Solar + storage project J1335, Jasper CountySolar + storage · 200 MW · built