🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Illinois

ONSHORE WIND · MISO

Onshore wind project J3860, Peoria County

Onshore wind project J3860, Peoria County is a 500 MW onshore wind request in interconnection study in the MISO interconnection queue, in Peoria County, Illinois, connecting to AMEREN ILLINOIS.

Queue statusIn planning
  1. PlanningQueued Jan 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3860
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN ILLINOIS
Connection point (POI)
7FARGO - 7SANDBURG 345.0kV
Location
Peoria County, Illinois
Technology
Wind: 500 MW
Total requested
500 MW
Service type
Network resource (NRIS)
Queue status
Active
Entered queue
27 January 2025
Proposed online date
April 2030

Location

Marker shows the centre of Peoria County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Peoria County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem