Pleasant Grove Solar

Pleasant Grove Solar is a 300 MW solar request in interconnection study in the PJM interconnection queue, in Mchenry County, Illinois, connecting to ComEd.

Queue statusIn planning
  1. PlanningQueued Mar 2020 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2023 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AF2-349
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ComEd
Developer
Deriva Energy Solar, LLC
Connection point (POI)
SILVER LAKE- CHERRY VALLEY 345 KV
Location
Mchenry County, Illinois
Technology
Solar: 300 MW
Total requested
300 MW
Service type
Energy only (ERIS)
Study phase
Available studies: Feasibility Study, System Impact Study
Queue status
Active
Entered queue
31 March 2020
Proposed online date
December 2023

Location

Marker shows the centre of Mchenry County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Mchenry County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem