United States › Grid › Interconnection queues › Illinois
GAS · MISOGas project J1839, Macon County
Gas project J1839, Macon County is a 340 MW gas request in interconnection study in the MISO interconnection queue, in Macon County, Illinois, connecting to AMEREN ILLINOIS.
Queue statusIn planning
- PlanningQueued Jun 2020 (current stage)
- ConsentedJun 2025 (not yet reached)
- Construction (not yet reached)
- OperatingTarget Nov 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J1839
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN ILLINOIS
- Connection point (POI)
- Decatur ADM North 138 kV
- Location
- Macon County, Illinois
- Technology
- Gas: 340 MW
- Total requested
- 340 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 25 June 2020
- Agreement signed
- 16 June 2025
- Proposed online date
- November 2026
Location
Marker shows the centre of Macon County; the queue data does not give exact sites.
Other requests in Macon County
- Onshore wind project J1115, Macon CountyOnshore wind · 200 MW · under construction
- Battery storage project J3417, Macon CountyBattery storage · 300 MW · in study
- Solar + storage project J2388, Macon CountySolar + storage · 200 MW · in study
- Solar project J2656, Macon CountySolar · 180 MW · in study
- Solar project J1677, Macon CountySolar · 180 MW · in study
- Battery storage project J2375, Macon CountyBattery storage · 100 MW · in study
- Battery storage project J2383, Macon CountyBattery storage · 100 MW · in study
- Radford's Run Wind FarmOnshore wind · 306 MW · built
- Onshore wind project J872, Macon CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project AA1-086, Macon CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project AD2-159, Macon CountyOnshore wind · 188 MW · withdrawn
- Onshore wind project J125, Macon CountyOnshore wind · 151 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem