Onshore wind project AA1-086, Macon County

Onshore wind project AA1-086, Macon County is a 200 MW onshore wind request withdrawn in the PJM interconnection queue, in Macon County, Illinois, connecting to ComEd.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2014 (completed)
  2. Withdrawn / abandonedFeb 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AA1-086
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ComEd
Connection point (POI)
Blue Mound-Latham
Location
Macon County, Illinois
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study
Queue status
Withdrawn
Entered queue
29 October 2014
Proposed online date
October 2017
Withdrawn
February 2016

Location

Marker shows the centre of Macon County; the queue data does not give exact sites.

Power plants in Illinois Β· Transmission lines in Illinois

Other requests in Macon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem