ONSHORE WIND Β· MISO

Onshore wind project J125, Macon County

Onshore wind project J125, Macon County is a 151 MW onshore wind request withdrawn in the MISO interconnection queue, in Macon County, Illinois.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2011 (completed)
  2. Withdrawn / abandonedMay 2012 (project stopped here)
  3. ConsentedMay 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J125
Grid region
MISO (Midcontinent)
Connection point (POI)
Latham - Maroa West 345 kV
Location
Macon County, Illinois
Technology
Wind: 151 MW
Total requested
151 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
22 August 2011
Agreement signed
11 May 2012
Proposed online date
May 2014
Withdrawn
May 2012

Location

Marker shows the centre of Macon County; the queue data does not give exact sites.

Power plants in Illinois Β· Transmission lines in Illinois

Other requests in Macon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem