United States › Grid › Interconnection queues › Illinois
ONSHORE WIND · MISOOnshore wind project J1115, Macon County
Onshore wind project J1115, Macon County is a 200 MW onshore wind request under construction in the MISO interconnection queue, in Macon County, Illinois, connecting to AMEREN ILLINOIS.
Queue statusUnder construction
- PlanningQueued Mar 2018 (completed)
- ConsentedOct 2021 (completed)
- Construction (current stage)
- OperatingTarget Sep 2024 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1115
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN ILLINOIS
- Connection point (POI)
- Latham - Oreana 345kV Line
- Location
- Macon County, Illinois
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Under Construction
- Queue status
- Active
- Entered queue
- 12 March 2018
- Agreement signed
- 12 October 2021
- Proposed online date
- September 2024
Location
Marker shows the centre of Macon County; the queue data does not give exact sites.
Other requests in Macon County
- Gas project J1839, Macon CountyGas · 340 MW · in study
- Battery storage project J3417, Macon CountyBattery storage · 300 MW · in study
- Solar + storage project J2388, Macon CountySolar + storage · 200 MW · in study
- Solar project J2656, Macon CountySolar · 180 MW · in study
- Solar project J1677, Macon CountySolar · 180 MW · in study
- Battery storage project J2375, Macon CountyBattery storage · 100 MW · in study
- Battery storage project J2383, Macon CountyBattery storage · 100 MW · in study
- Radford's Run Wind FarmOnshore wind · 306 MW · built
- Onshore wind project J872, Macon CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project AA1-086, Macon CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project AD2-159, Macon CountyOnshore wind · 188 MW · withdrawn
- Onshore wind project J125, Macon CountyOnshore wind · 151 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem