ONSHORE WIND · MISOOnshore wind project J3730, Macoupin County
Onshore wind project J3730, Macoupin County is a 444 MW onshore wind request in interconnection study in the MISO interconnection queue, in Macoupin County, Illinois, connecting to AMEREN ILLINOIS.
Queue statusIn planning
- PlanningQueued Apr 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Aug 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3730
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN ILLINOIS
- Connection point (POI)
- MORO 345 kV Substation
- Location
- Macoupin County, Illinois
- Technology
- Wind: 444 MW
- Total requested
- 444 MW
- Service type
- Energy only (ERIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Active
- Entered queue
- 18 April 2024
- Proposed online date
- August 2028
Location
Marker shows the centre of Macoupin County; the queue data does not give exact sites.
Other requests in Macoupin County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem