SOLAR + STORAGE · MISO

Solar + storage project J3076, Wabash County

Solar + storage project J3076, Wabash County is a 500 MW solar + storage request in interconnection study in the MISO interconnection queue, in Wabash County, Illinois, connecting to DUKE ENERGY INDIANA.

Queue statusIn planning
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3076
Grid region
MISO (Midcontinent)
Utility / transmission owner
DUKE ENERGY INDIANA
Connection point (POI)
08GIBSON (PSI) - 7ALBION 345.0kV
Location
Wabash County, Illinois
Technology
Solar: 500 MW · Battery
Total requested
500 MW
Service type
Energy only (ERIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Active
Entered queue
15 September 2022
Proposed online date
November 2025

Location

Marker shows the centre of Wabash County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Wabash County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem