United States › Grid › Interconnection queues › Rhode Island
OFFSHORE WIND · ISO-NERevoultion Offshore wind
Revoultion Offshore wind is a 704 MW offshore wind request with a signed interconnection agreement in the ISO-NE interconnection queue.
Queue statusConsented
- PlanningQueued Sep 2018 (completed)
- ConsentedMay 2023 (current stage)
- Construction (not yet reached)
- OperatingTarget Nov 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 781
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- NG 115 kV Davisville substation, Washington County
- Location
- Rhode Island
- Technology
- Offshore Wind: 704 MW
- Total requested
- 704 MW
- Service type
- Energy only (ERIS)
- Study phase
- Executed
- Queue status
- Active
- Entered queue
- 13 September 2018
- Agreement signed
- 3 May 2023
- Proposed online date
- November 2026
Location
No county location in the queue data.
Power plants in Rhode Island · Transmission lines in Rhode Island
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem