United States βΊ Grid βΊ Interconnection queues βΊ West Virginia
COAL Β· PJMMountaineer #1
Mountaineer #1 is a 36.0 MW coal request with a signed interconnection agreement in the PJM interconnection queue, connecting to AEP.
Queue statusConsented
- PlanningQueued Oct 2015 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingDec 2018 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- AB1-109
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Mountaineer
- Location
- West Virginia
- Technology
- Coal: 36.0 MW
- Total requested
- 36.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Active
- Entered queue
- 26 October 2015
- Proposed online date
- June 2021
- Came online
- December 2018
Location
No county location in the queue data.
Power plants in West Virginia Β· Transmission lines in West Virginia
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem