United States › Grid › Interconnection queues › West Virginia
HYDRO · PJMHawks Nest Hydro
Hawks Nest Hydro is a 51.0 MW hydro request with a signed interconnection agreement in the PJM interconnection queue, in Fayette County, West Virginia, connecting to AEP.
Queue statusConsented
- PlanningQueued Mar 2019 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Sep 2028 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- AE2-160
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Kanawha River 138 kV
- Location
- Fayette County, West Virginia
- Technology
- Hydro: 51.0 MW
- Total requested
- 51.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Active
- Entered queue
- 15 March 2019
- Proposed online date
- September 2028
Location
Marker shows the centre of Fayette County; the queue data does not give exact sites.
Power plants in West Virginia · Transmission lines in West Virginia
Other requests in Fayette County
- Solar project AG2-657, Fayette CountySolar · 90.0 MW · in study
- Hawks Nest HydroHydro · 54.2 MW · built
- Hydro project O57, Fayette CountyHydro · 142 MW · withdrawn
- Solar + storage project AG1-194, Fayette CountySolar + storage · 79.0 MW · withdrawn
- Solar + storage project AG1-219, Fayette CountySolar + storage · 75.0 MW · withdrawn
- STOther · 53.0 MW · withdrawn
- Hydro project AE2-159, Fayette CountyHydro · 48.0 MW · withdrawn
- Other project W3-161, Fayette CountyOther · 13.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem