United States βΊ Grid βΊ Interconnection queues βΊ West Virginia
OTHER Β· PJMST
ST is a 53.0 MW other request withdrawn in the PJM interconnection queue, in Fayette County, West Virginia, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2009 (completed)
- Withdrawn / abandonedJan 2013 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- V1-035
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Kanawha 138kV
- Location
- Fayette County, West Virginia
- Technology
- Other: 53.0 MW
- Total requested
- 53.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 30 April 2009
- Proposed online date
- May 2011
- Withdrawn
- January 2013
Location
Marker shows the centre of Fayette County; the queue data does not give exact sites.
Power plants in West Virginia Β· Transmission lines in West Virginia
Other requests in Fayette County
- Hawks Nest HydroHydro Β· 51.0 MW Β· agreement signed
- Solar project AG2-657, Fayette CountySolar Β· 90.0 MW Β· in study
- Hawks Nest HydroHydro Β· 54.2 MW Β· built
- Hydro project O57, Fayette CountyHydro Β· 142 MW Β· withdrawn
- Solar + storage project AG1-194, Fayette CountySolar + storage Β· 79.0 MW Β· withdrawn
- Solar + storage project AG1-219, Fayette CountySolar + storage Β· 75.0 MW Β· withdrawn
- Hydro project AE2-159, Fayette CountyHydro Β· 48.0 MW Β· withdrawn
- Other project W3-161, Fayette CountyOther Β· 13.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem