United States › Grid › Interconnection queues › West Virginia
SOLAR + STORAGE · PJMSolar + storage project AH2-043, Kanawha County
Solar + storage project AH2-043, Kanawha County is a 200 MW solar + storage request in interconnection study in the PJM interconnection queue, in Kanawha County, West Virginia, connecting to AEP.
- PlanningQueued Nov 2021 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AH2-043
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Cabin Creek 138 kV
- Location
- Kanawha County, West Virginia
- Technology
- Solar: 200 MW · Battery
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Active
- Entered queue
- 19 November 2021
- Proposed online date
- December 2025
Location
Marker shows the centre of Kanawha County; the queue data does not give exact sites.
Power plants in West Virginia · Transmission lines in West Virginia
Other requests in Kanawha County
- Kanawna River #2Coal · 5.0 MW · built
- Kanawna River #1Coal · 5.0 MW · built
- Charleston Clean EnergyOther · 3.2 MW · built
- Charlston LFOther · 2.0 MW · built
- Solar project AG2-656, Kanawha CountySolar · 100 MW · withdrawn
- Battery storage project AH2-278, Kanawha CountyBattery storage · 100 MW · withdrawn
- Solar + storage project AH2-209, Kanawha CountySolar + storage · 95.0 MW · withdrawn
- Battery storage project AH1-426, Kanawha CountyBattery storage · 64.6 MW · withdrawn
- Solar + storage project AD1-149, Kanawha CountySolar + storage · 19.9 MW · withdrawn
- Gas project O37, Kanawha CountyGas · 14.0 MW · withdrawn
- Solar project AH2-134, Kanawha CountySolar · 5.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem