United States › Grid › Interconnection queues › West Virginia
OTHER · PJMCharlston LF
Charlston LF is a 2.0 MW other request built and operating in the PJM interconnection queue, in Kanawha County, West Virginia, connecting to AEP.
Request details
- Queue ID
- V1-023
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Bridge 12kV
- Location
- Kanawha County, West Virginia
- Technology
- Other: 2.0 MW
- Total requested
- 2.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
- Queue status
- Operational
- Entered queue
- 6 April 2009
- Proposed online date
- December 2010
- Came online
- December 2010
Location
Marker shows the centre of Kanawha County; the queue data does not give exact sites.
Power plants in West Virginia · Transmission lines in West Virginia
Other requests in Kanawha County
- Solar + storage project AH2-043, Kanawha CountySolar + storage · 200 MW · in study
- Kanawna River #2Coal · 5.0 MW · built
- Kanawna River #1Coal · 5.0 MW · built
- Charleston Clean EnergyOther · 3.2 MW · built
- Solar project AG2-656, Kanawha CountySolar · 100 MW · withdrawn
- Battery storage project AH2-278, Kanawha CountyBattery storage · 100 MW · withdrawn
- Solar + storage project AH2-209, Kanawha CountySolar + storage · 95.0 MW · withdrawn
- Battery storage project AH1-426, Kanawha CountyBattery storage · 64.6 MW · withdrawn
- Solar + storage project AD1-149, Kanawha CountySolar + storage · 19.9 MW · withdrawn
- Gas project O37, Kanawha CountyGas · 14.0 MW · withdrawn
- Solar project AH2-134, Kanawha CountySolar · 5.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem