Raleigh Solar Project

Raleigh Solar Project is a 90.0 MW solar request suspended in the PJM interconnection queue, in Raleigh County, West Virginia, connecting to AEP.

Queue statusPaused / redesign
  1. PlanningQueued Sep 2018 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AE1-212
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Grandview-Clifftop 138 kV
Location
Raleigh County, West Virginia
Technology
Solar: 90.0 MW
Total requested
90.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Suspended
Entered queue
10 September 2018
Proposed online date
June 2025

Location

Marker shows the centre of Raleigh County; the queue data does not give exact sites.

Power plants in West Virginia · Transmission lines in West Virginia

Other requests in Raleigh County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem