United States › Grid › Interconnection queues › Delaware
OFFSHORE WIND · PJMMaryland Offshore Wind Energy Project (MOWEP)
Maryland Offshore Wind Energy Project (MOWEP) is a 248 MW offshore wind request suspended in the PJM interconnection queue, in Sussex County, Delaware, connecting to DPL.
Queue statusPaused / redesign
- PlanningQueued Aug 2015 (current stage)
- ConsentedAug 2018 (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AB1-056
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- DPL
- Connection point (POI)
- Indian River 230kV I
- Location
- Sussex County, Delaware
- Technology
- Offshore Wind: 248 MW
- Total requested
- 248 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Suspended
- Entered queue
- 31 August 2015
- Agreement signed
- 28 August 2018
- Proposed online date
- December 2027
Location
Marker shows the centre of Sussex County; the queue data does not give exact sites.
Other requests in Sussex County
- Battery storage project AH2-077, Sussex CountyBattery storage · 150 MW · in study
- Solar project AH1-672, Sussex CountySolar · 75.0 MW · in study
- Maryland Offshore Wind Energy Project (MOWEP)Offshore wind · 7.3 MW · suspended
- Indian River Units 3-4Coal · 18.0 MW · built
- DuPont SeafordGas · 10.0 MW · built
- Southern LF Units 1-5Other · 5.0 MW · built
- Indian River Units #3 & #4Coal · 5.0 MW · built
- Southern Landfill Units 1-4Other · 1.0 MW · built
- Offshore wind project AH1-384, Sussex CountyOffshore wind · 1,410 MW · withdrawn
- Offshore wind project AH1-278, Sussex CountyOffshore wind · 1,035 MW · withdrawn
- Offshore wind project AH1-277, Sussex CountyOffshore wind · 1,035 MW · withdrawn
- Offshore wind project AG2-348, Sussex CountyOffshore wind · 898 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem