United States › Grid › Interconnection queues › Florida

BATTERY STORAGE · SOUTHEAST

Battery storage project FC100380, Citrus County

Battery storage project FC100380, Citrus County is a 199 MW battery storage request in interconnection study in the Southeast interconnection queue, in Citrus County, Florida, connecting to Duke Energy Florida.

Queue statusIn planning
  1. PlanningQueued Dec 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
FC100380
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Florida
Developer
Duke Energy Florida, LLC
Connection point (POI)
Citrus Combined Cycle 230 kV Substation
Location
Citrus County, Florida
Technology
Battery: 199 MW
Total requested
199 MW
Service type
NRIS and ERIS
Study phase
In Progress (unknown study)
Queue status
Active
Entered queue
8 December 2025
Proposed online date
June 2030

Location

Marker shows the centre of Citrus County; the queue data does not give exact sites.

Power plants in Florida · Transmission lines in Florida

Other requests in Citrus County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem