United States › Grid › Interconnection queues › Florida
BATTERY STORAGE · SOUTHEASTBattery storage project 327, Citrus County
Battery storage project 327, Citrus County is a 100 MW battery storage request under construction in the Southeast interconnection queue, in Citrus County, Florida, connecting to Duke Energy Florida.
Queue statusUnder construction
- PlanningQueued May 2023 (completed)
- Consented (completed)
- Construction (current stage)
- OperatingTarget Mar 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 327
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Duke Energy Florida
- Developer
- Duke Energy Florida, LLC
- Connection point (POI)
- Powerline Substation
- Location
- Citrus County, Florida
- Technology
- Battery: 100 MW
- Total requested
- 100 MW
- Service type
- Energy only (ERIS)
- Study phase
- Construction
- Queue status
- Active
- Entered queue
- 5 May 2023
- Proposed online date
- March 2027
Location
Marker shows the centre of Citrus County; the queue data does not give exact sites.
Other requests in Citrus County
- Battery storage project FC100380, Citrus CountyBattery storage · 199 MW · in study
- Gas project 123, Citrus CountyGas · 940 MW · built
- Gas project 124, Citrus CountyGas · 940 MW · built
- Solar project 199, Citrus CountySolar · 74.9 MW · built
- Coal project 42, Citrus CountyCoal · 10.0 MW · built
- Coal project 43, Citrus CountyCoal · 10.0 MW · built
- Coal project 45, Citrus CountyCoal · 10.0 MW · built
- Coal project 44, Citrus CountyCoal · 10.0 MW · built
- Gas project 111, Citrus CountyGas · 950 MW · withdrawn
- Gas project 10, Citrus CountyGas · 700 MW · withdrawn
- Nuclear project 41, Citrus CountyNuclear · 140 MW · withdrawn
- Solar project 198, Citrus CountySolar · 74.9 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem