Malta Project

Malta Project is a 225 MW battery storage request in interconnection study in the Southeast interconnection queue, in Brevard County, Florida, connecting to Orlando Utilities Commission.

Queue statusIn planning
  1. PlanningQueued Mar 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
202311
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Orlando Utilities Commission
Connection point (POI)
OUC Indian River Plant
Location
Brevard County, Florida
Technology
Battery: 225 MW
Total requested
225 MW
Service type
Network resource (NRIS)
Study phase
Facility Study
Queue status
Active
Entered queue
6 March 2023
Proposed online date
December 2026

Location

Marker shows the centre of Brevard County; the queue data does not give exact sites.

Power plants in Florida · Transmission lines in Florida

Other requests in Brevard County