SOLAR · SOUTHEASTSolar project 357, Brevard County
Solar project 357, Brevard County is a 74.5 MW solar request in interconnection study in the Southeast interconnection queue, in Brevard County, Florida, connecting to Florida Power & Light.
Queue statusIn planning
- PlanningQueued Jul 2018 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jul 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 357
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Florida Power & Light
- Developer
- FPL
- Connection point (POI)
- Heritage Solar-Malabar 230kV
- Location
- Brevard County, Florida
- Technology
- Solar: 74.5 MW
- Total requested
- 74.5 MW
- Service type
- Network resource (NRIS)
- Study phase
- Facility Study
- Queue status
- Active
- Entered queue
- 30 July 2018
- Proposed online date
- July 2028
Location
Marker shows the centre of Brevard County; the queue data does not give exact sites.
Other requests in Brevard County
- Malta ProjectBattery storage · 225 MW · in study
- Solar project 358, Brevard CountySolar · 74.5 MW · in study
- Solar project 306, Brevard CountySolar · 74.5 MW · in study
- Solar project 302, Brevard CountySolar · 74.5 MW · built
- Solar project 356, Brevard CountySolar · 74.5 MW · built
- Solar project 355, Brevard CountySolar · 74.5 MW · built
- Solar project 203, Brevard CountySolar · 74.5 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem