🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Florida

SOLAR · SOUTHEAST

Solar project 356, Brevard County

Solar project 356, Brevard County is a 74.5 MW solar request built and operating in the Southeast interconnection queue, in Brevard County, Florida, connecting to Florida Power & Light.

Queue statusOperating
  1. PlanningQueued Jul 2018 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJan 2025 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
356
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Florida Power & Light
Developer
FPL
Connection point (POI)
Heritage Solar-Malabar 230kV
Location
Brevard County, Florida
Technology
Solar: 74.5 MW
Total requested
74.5 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
30 July 2018
Proposed online date
January 2025
Came online
January 2025

Location

Marker shows the centre of Brevard County; the queue data does not give exact sites.

Power plants in Florida · Transmission lines in Florida

Other requests in Brevard County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem