United States › Grid › Interconnection queues › Florida

GAS · SOUTHEAST

Gas project FC100386, Osceola County

Gas project FC100386, Osceola County is a 265 MW gas request in interconnection study in the Southeast interconnection queue, in Osceola County, Florida, connecting to Duke Energy Florida.

Queue statusIn planning
  1. PlanningQueued Dec 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
FC100386
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Florida
Developer
Duke Energy Florida, LLC
Connection point (POI)
Intercession City 230 kV Substation
Location
Osceola County, Florida
Technology
Gas: 265 MW
Total requested
265 MW
Service type
Network resource (NRIS)
Study phase
In Progress (unknown study)
Queue status
Active
Entered queue
15 December 2025
Proposed online date
December 2030

Location

Marker shows the centre of Osceola County; the queue data does not give exact sites.

Power plants in Florida · Transmission lines in Florida