🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Florida

SOLAR · SOUTHEAST

Harmony 2

Harmony 2 is a 74.5 MW solar request in interconnection study in the Southeast interconnection queue, in Osceola County, Florida, connecting to Orlando Utilities Commission.

Queue statusIn planning
  1. PlanningQueued Dec 2020 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
202003
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Orlando Utilities Commission
Connection point (POI)
St Cloud East - Holopaw 230 kV (Rocky Pond Station)
Location
Osceola County, Florida
Technology
Solar: 74.5 MW
Total requested
74.5 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Active
Entered queue
9 December 2020
Proposed online date
December 2024

Location

Marker shows the centre of Osceola County; the queue data does not give exact sites.

Power plants in Florida · Transmission lines in Florida

Other requests in Osceola County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem