Storey Bend

Storey Bend is a 74.5 MW solar request in interconnection study in the Southeast interconnection queue, in Osceola County, Florida, connecting to Orlando Utilities Commission.

Queue statusIn planning
  1. PlanningQueued Feb 2018 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
201801
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Orlando Utilities Commission
Connection point (POI)
St Cloud East - Magnolia Ranch 230 kV Tap
Location
Osceola County, Florida
Technology
Solar: 74.5 MW
Total requested
74.5 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Active
Entered queue
1 February 2018
Proposed online date
December 2024

Location

Marker shows the centre of Osceola County; the queue data does not give exact sites.