🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Florida

GAS · SOUTHEAST

Gas project 415, Manatee County

Gas project 415, Manatee County is a 87.0 MW gas request in interconnection study in the Southeast interconnection queue, in Manatee County, Florida, connecting to Florida Power & Light.

Queue statusIn planning
  1. PlanningQueued Sep 2020 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
415
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Florida Power & Light
Developer
FPL
Connection point (POI)
Manatee Sub
Location
Manatee County, Florida
Technology
Gas: 87.0 MW
Total requested
87.0 MW
Service type
Network resource (NRIS)
Study phase
Facility Study
Queue status
Active
Entered queue
14 September 2020
Proposed online date
December 2026

Location

Marker shows the centre of Manatee County; the queue data does not give exact sites.

Power plants in Florida · Transmission lines in Florida

Other requests in Manatee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem