BATTERY STORAGE · SOUTHEASTBattery storage project 371, Manatee County
Battery storage project 371, Manatee County is a 409 MW battery storage request built and operating in the Southeast interconnection queue, in Manatee County, Florida, connecting to Florida Power & Light.
Request details
- Queue ID
- 371
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Florida Power & Light
- Developer
- FPL
- Connection point (POI)
- Manatee Sub
- Location
- Manatee County, Florida
- Technology
- Battery: 409 MW
- Total requested
- 409 MW
- Service type
- Network resource (NRIS)
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 18 October 2019
- Came online
- November 2021
Location
Marker shows the centre of Manatee County; the queue data does not give exact sites.
Other requests in Manatee County
- Gas project 415, Manatee CountyGas · 87.0 MW · in study
- Solar project 511, Manatee CountySolar · 74.5 MW · in study
- Solar project 437, Manatee CountySolar · 74.5 MW · in study
- Solar project 191, Manatee CountySolar · 74.5 MW · in study
- Solar project 509, Manatee CountySolar · 74.5 MW · in study
- Solar project 433, Manatee CountySolar · 74.5 MW · in study
- Solar project 424, Manatee CountySolar · 74.5 MW · in study
- Solar project 510, Manatee CountySolar · 74.5 MW · in study
- Solar project 428, Manatee CountySolar · 74.5 MW · in study
- Solar project 422, Manatee CountySolar · 74.5 MW · built
- Solar project 361, Manatee CountySolar · 74.5 MW · built
- Solar project 194, Manatee CountySolar · 74.5 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem