BATTERY STORAGE · WESTBattery storage project G0965, Umatilla County
Battery storage project G0965, Umatilla County is a 650 MW battery storage request in interconnection study in the West interconnection queue, in Umatilla County, Oregon.
Queue statusIn planning
- PlanningQueued Oct 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2032 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- G0965
- Grid region
- West (non-ISO utilities)
- Connection point (POI)
- Stanfield Substation at 230 kV
- Location
- Umatilla County, Oregon
- Technology
- Battery: 650 MW
- Total requested
- 650 MW
- Service type
- NRIS and ERIS
- Study phase
- In Progress (unknown study)
- Queue status
- Active
- Entered queue
- 11 October 2023
- Proposed online date
- December 2032
Location
Marker shows the centre of Umatilla County; the queue data does not give exact sites.
Other requests in Umatilla County
- Solar + storage project C2-175, Umatilla CountySolar + storage · 80.0 MW · agreement signed
- Solar + storage project G0777, Umatilla CountySolar + storage · 1,300 MW · in study
- Battery storage project G0778, Umatilla CountyBattery storage · 650 MW · in study
- Other project G0854, Umatilla CountyOther · 600 MW · in study
- Solar + storage project G0908, Umatilla CountySolar + storage · 500 MW · in study
- Onshore wind project G1013, Umatilla CountyOnshore wind · 250 MW · in study
- Solar + storage project G1062, Umatilla CountySolar + storage · 205 MW · in study
- Solar + storage project G1063, Umatilla CountySolar + storage · 175 MW · in study
- Solar + storage project G0738, Umatilla CountySolar + storage · 85.0 MW · in study
- Solar + storage project PIS104, Umatilla CountySolar + storage · 80.0 MW · in study
- Onshore wind project G1012, Umatilla CountyOnshore wind · 67.0 MW · in study
- Gas project G0620, Umatilla CountyGas · 27.0 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem