United States › Grid › Interconnection queues › Oregon

SOLAR + STORAGE · WEST

Solar + storage project G1062, Umatilla County

Solar + storage project G1062, Umatilla County is a 205 MW solar + storage request in interconnection study in the West interconnection queue, in Umatilla County, Oregon.

Queue statusIn planning
  1. PlanningQueued Jan 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
G1062
Grid region
West (non-ISO utilities)
Connection point (POI)
Longhorn 230kV
Location
Umatilla County, Oregon
Technology
Solar: 130 MW · Battery: 75.0 MW
Total requested
205 MW
Service type
Energy only (ERIS)
Study phase
In Progress (unknown study)
Queue status
Active
Entered queue
22 January 2024
Proposed online date
December 2026

Location

Marker shows the centre of Umatilla County; the queue data does not give exact sites.

Power plants in Oregon · Transmission lines in Oregon

Other requests in Umatilla County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem