🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Nevada

SOLAR + STORAGE · CAISO

Water Rock Solar 2

Water Rock Solar 2 is a 1,034 MW solar + storage request in interconnection study in the CAISO interconnection queue, in Nye County, Nevada, connecting to GLW.

Queue statusIn planning
  1. PlanningQueued Apr 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
2146
Grid region
CAISO (California)
Utility / transmission owner
GLW
Connection point (POI)
Gamebird Substation 230 kV
Location
Nye County, Nevada
Technology
Solar: 517 MW · Battery: 517 MW
Total requested
1,034 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Active
Entered queue
15 April 2021
Proposed online date
December 2028

Location

Marker shows the centre of Nye County; the queue data does not give exact sites.

Power plants in Nevada · Transmission lines in Nevada

Other requests in Nye County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem