United States › Grid › Interconnection queues › Nevada

SOLAR + STORAGE · CAISO

Rough Hat Hybrid Solar

Rough Hat Hybrid Solar is a 404 MW solar + storage request with a signed interconnection agreement in the CAISO interconnection queue, in Nye County, Nevada, connecting to GLW.

Queue statusConsented
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedApr 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1650
Grid region
CAISO (California)
Utility / transmission owner
GLW
Connection point (POI)
Trout Canyon Substation 230 kV
Location
Nye County, Nevada
Technology
Solar: 204 MW · Battery: 200 MW
Total requested
404 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
15 April 2019
Agreement signed
27 April 2024
Proposed online date
July 2028

Location

Marker shows the centre of Nye County; the queue data does not give exact sites.

Power plants in Nevada · Transmission lines in Nevada

Other requests in Nye County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem