WIND + STORAGE · WEST

Wind + storage project Company LV, White Pine County

Wind + storage project Company LV, White Pine County is a 600 MW wind + storage request suspended in the West interconnection queue, in White Pine County, Nevada, connecting to NV Energy.

Queue statusPaused / redesign
  1. PlanningQueued Sep 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Company LV
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
White Pine County, Nevada
Technology
Wind: 600 MW · Battery
Total requested
600 MW
Service type
Network resource (NRIS)
Queue status
Suspended
Entered queue
28 September 2021
Proposed online date
October 2025

Location

Marker shows the centre of White Pine County; the queue data does not give exact sites.