United States › Grid › Interconnection queues › Nevada
SOLAR + STORAGE · WESTSolar + storage project Company MW, White Pine County
Solar + storage project Company MW, White Pine County is a 400 MW solar + storage request with a signed interconnection agreement in the West interconnection queue, in White Pine County, Nevada, connecting to NV Energy.
Queue statusConsented
- PlanningQueued Mar 2022 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2030 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- Company MW
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- NV Energy
- Location
- White Pine County, Nevada
- Technology
- Solar: 400 MW · Battery
- Total requested
- 400 MW
- Service type
- NRIS and ERIS
- Study phase
- IA Executed
- Queue status
- Active
- Entered queue
- 28 March 2022
- Proposed online date
- December 2030
Location
Marker shows the centre of White Pine County; the queue data does not give exact sites.
Other requests in White Pine County
- Other project Company KR, White Pine CountyOther · 600 MW · agreement signed
- Solar + storage project Company MB, White Pine CountySolar + storage · 300 MW · agreement signed
- Solar + storage project Company MA, White Pine CountySolar + storage · 300 MW · agreement signed
- Battery storage project Company QH, White Pine CountyBattery storage · 200 MW · in study
- Other project Company KD, White Pine CountyOther · 750 MW · suspended
- Solar + storage project Company NU, White Pine CountySolar + storage · 600 MW · suspended
- Solar + storage project Company NX, White Pine CountySolar + storage · 600 MW · suspended
- Solar + storage project Company NW, White Pine CountySolar + storage · 600 MW · suspended
- Solar + storage project Company NQ, White Pine CountySolar + storage · 600 MW · suspended
- Wind + storage project Company LV, White Pine CountyWind + storage · 600 MW · suspended
- Battery storage project Company MV, White Pine CountyBattery storage · 550 MW · suspended
- Solar + storage project Company NB, White Pine CountySolar + storage · 350 MW · suspended
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem