United States › Grid › Interconnection queues › Nevada
BATTERY STORAGE · WESTBattery storage project Company QH, White Pine County
Battery storage project Company QH, White Pine County is a 200 MW battery storage request in interconnection study in the West interconnection queue, in White Pine County, Nevada, connecting to NV Energy.
- PlanningQueued Sep 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jan 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- Company QH
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- NV Energy
- Location
- White Pine County, Nevada
- Technology
- Battery: 200 MW
- Total requested
- 200 MW
- Service type
- NRIS and ERIS
- Study phase
- In Progress (unknown study)
- Queue status
- Active
- Entered queue
- 25 September 2023
- Proposed online date
- January 2026
Location
Marker shows the centre of White Pine County; the queue data does not give exact sites.
Other requests in White Pine County
- Other project Company KR, White Pine CountyOther · 600 MW · agreement signed
- Solar + storage project Company MW, White Pine CountySolar + storage · 400 MW · agreement signed
- Solar + storage project Company MB, White Pine CountySolar + storage · 300 MW · agreement signed
- Solar + storage project Company MA, White Pine CountySolar + storage · 300 MW · agreement signed
- Other project Company KD, White Pine CountyOther · 750 MW · suspended
- Solar + storage project Company NU, White Pine CountySolar + storage · 600 MW · suspended
- Solar + storage project Company NX, White Pine CountySolar + storage · 600 MW · suspended
- Solar + storage project Company NW, White Pine CountySolar + storage · 600 MW · suspended
- Solar + storage project Company NQ, White Pine CountySolar + storage · 600 MW · suspended
- Wind + storage project Company LV, White Pine CountyWind + storage · 600 MW · suspended
- Battery storage project Company MV, White Pine CountyBattery storage · 550 MW · suspended
- Solar + storage project Company NB, White Pine CountySolar + storage · 350 MW · suspended
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem