United States › Grid › Interconnection queues › Kansas

SOLAR · SPP

Solar project GEN-2022-015, Decatur County

Solar project GEN-2022-015, Decatur County is a 270 MW solar request in interconnection study in the SPP interconnection queue, in Decatur County, Kansas, connecting to SUNC.

Queue statusIn planning
  1. PlanningQueued Jun 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2022-015
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SUNC
Connection point (POI)
Tap of Mingo - Red Willow 345 kV Line
Location
Decatur County, Kansas
Technology
Solar: 270 MW
Total requested
270 MW
Service type
NRIS and ERIS
Study phase
FACILITY STUDY STAGE
Queue status
Active
Entered queue
8 June 2022
Proposed online date
December 2028

Location

Marker shows the centre of Decatur County; the queue data does not give exact sites.

Power plants in Kansas · Transmission lines in Kansas

Other requests in Decatur County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem