United States › Grid › Interconnection queues › Kansas
SOLAR · SPPSolar project GEN-2022-015, Decatur County
Solar project GEN-2022-015, Decatur County is a 270 MW solar request in interconnection study in the SPP interconnection queue, in Decatur County, Kansas, connecting to SUNC.
Queue statusIn planning
- PlanningQueued Jun 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2022-015
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SUNC
- Connection point (POI)
- Tap of Mingo - Red Willow 345 kV Line
- Location
- Decatur County, Kansas
- Technology
- Solar: 270 MW
- Total requested
- 270 MW
- Service type
- NRIS and ERIS
- Study phase
- FACILITY STUDY STAGE
- Queue status
- Active
- Entered queue
- 8 June 2022
- Proposed online date
- December 2028
Location
Marker shows the centre of Decatur County; the queue data does not give exact sites.
Other requests in Decatur County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem