Onshore wind project GEN-2022-161, Butler County

Onshore wind project GEN-2022-161, Butler County is a 360 MW onshore wind request in interconnection study in the SPP interconnection queue, in Butler County, Kansas, connecting to WERE.

Queue statusIn planning
  1. PlanningQueued Feb 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2022-161
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WERE
Connection point (POI)
Burns 345kV Substation
Location
Butler County, Kansas
Technology
Wind: 360 MW
Total requested
360 MW
Service type
Energy only (ERIS)
Study phase
FACILITY STUDY STAGE
Queue status
Active
Entered queue
24 February 2023
Proposed online date
January 2029

Location

Marker shows the centre of Butler County; the queue data does not give exact sites.