ONSHORE WIND · SPPOnshore wind project GEN-2024-016, Smith County
Onshore wind project GEN-2024-016, Smith County is a 300 MW onshore wind request in interconnection study in the SPP interconnection queue, in Smith County, Kansas, connecting to ITCGP.
Queue statusIn planning
- PlanningQueued Oct 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2024-016
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- ITCGP
- Connection point (POI)
- Post Rock - Macon 345 kV Line
- Location
- Smith County, Kansas
- Technology
- Wind: 300 MW
- Total requested
- 300 MW
- Service type
- NRIS and ERIS
- Study phase
- DISIS STAGE
- Queue status
- Active
- Entered queue
- 30 October 2024
- Proposed online date
- December 2028
Location
Marker shows the centre of Smith County; the queue data does not give exact sites.
Other requests in Smith County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem