ONSHORE WIND · SPP

Onshore wind project GEN-2024-016, Smith County

Onshore wind project GEN-2024-016, Smith County is a 300 MW onshore wind request in interconnection study in the SPP interconnection queue, in Smith County, Kansas, connecting to ITCGP.

Queue statusIn planning
  1. PlanningQueued Oct 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2024-016
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
ITCGP
Connection point (POI)
Post Rock - Macon 345 kV Line
Location
Smith County, Kansas
Technology
Wind: 300 MW
Total requested
300 MW
Service type
NRIS and ERIS
Study phase
DISIS STAGE
Queue status
Active
Entered queue
30 October 2024
Proposed online date
December 2028

Location

Marker shows the centre of Smith County; the queue data does not give exact sites.

Power plants in Kansas · Transmission lines in Kansas

Other requests in Smith County