🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Kansas

ONSHORE WIND · SPP

Onshore wind project GEN-2024-144, Scott County

Onshore wind project GEN-2024-144, Scott County is a 300 MW onshore wind request in interconnection study in the SPP interconnection queue, in Scott County, Kansas, connecting to SUNC.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2024-144
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SUNC
Connection point (POI)
Setab 345 kV Substation
Location
Scott County, Kansas
Technology
Wind: 300 MW
Total requested
300 MW
Service type
NRIS and ERIS
Study phase
DISIS STAGE
Queue status
Active
Entered queue
1 March 2025
Proposed online date
December 2030

Location

Marker shows the centre of Scott County; the queue data does not give exact sites.

Power plants in Kansas · Transmission lines in Kansas

Other requests in Scott County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem