United States › Grid › Interconnection queues › Kansas
SOLAR · SPPSolar project GEN-2024-136, Scott County
Solar project GEN-2024-136, Scott County is a 400 MW solar request in interconnection study in the SPP interconnection queue, in Scott County, Kansas, connecting to SUNC.
Queue statusIn planning
- PlanningQueued Mar 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2024-136
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SUNC
- Connection point (POI)
- Setab 345 kV Substation
- Location
- Scott County, Kansas
- Technology
- Solar: 400 MW
- Total requested
- 400 MW
- Service type
- NRIS and ERIS
- Study phase
- DISIS STAGE
- Queue status
- Active
- Entered queue
- 1 March 2025
- Proposed online date
- December 2029
Location
Marker shows the centre of Scott County; the queue data does not give exact sites.
Other requests in Scott County
- Onshore wind project GEN-2024-137, Scott CountyOnshore wind · 300 MW · in study
- Onshore wind project GEN-2024-138, Scott CountyOnshore wind · 300 MW · in study
- Onshore wind project GEN-2024-144, Scott CountyOnshore wind · 300 MW · in study
- Onshore wind project GEN-2024-108, Scott CountyOnshore wind · 302 MW · withdrawn
- Onshore wind project GEN-2008-017, Scott CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project GEN-2023-047, Scott CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project GEN-2023-046, Scott CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project GEN-2023-045, Scott CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project GEN-2023-048, Scott CountyOnshore wind · 250 MW · withdrawn
- Solar project GEN-2023-043, Scott CountySolar · 200 MW · withdrawn
- Solar project GEN-2023-044, Scott CountySolar · 200 MW · withdrawn
- Solar project GEN-2022-124, Scott CountySolar · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem