Solar project GEN-2024-136, Scott County

Solar project GEN-2024-136, Scott County is a 400 MW solar request in interconnection study in the SPP interconnection queue, in Scott County, Kansas, connecting to SUNC.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2024-136
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SUNC
Connection point (POI)
Setab 345 kV Substation
Location
Scott County, Kansas
Technology
Solar: 400 MW
Total requested
400 MW
Service type
NRIS and ERIS
Study phase
DISIS STAGE
Queue status
Active
Entered queue
1 March 2025
Proposed online date
December 2029

Location

Marker shows the centre of Scott County; the queue data does not give exact sites.

Power plants in Kansas · Transmission lines in Kansas

Other requests in Scott County