SOLAR + STORAGE · SPPSolar + storage project GEN-2020-008, Stevens County
Solar + storage project GEN-2020-008, Stevens County is a 250 MW solar + storage request with a signed interconnection agreement in the SPP interconnection queue, in Stevens County, Kansas, connecting to SPS.
Queue statusConsented
- PlanningQueued Apr 2020 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Jun 2028 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GEN-2020-008
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SPS
- Connection point (POI)
- Corporation Carpenter 345kV Substation
- Location
- Stevens County, Kansas
- Technology
- Solar: 250 MW · Battery
- Total requested
- 250 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA FULLY EXECUTED/ON SCHEDULE
- Queue status
- Active
- Entered queue
- 22 April 2020
- Proposed online date
- June 2028
Location
Marker shows the centre of Stevens County; the queue data does not give exact sites.
Other requests in Stevens County
- Solar project GEN-2024-032, Stevens CountySolar · 250 MW · in study
- Onshore wind project GEN-2021-021, Stevens CountyOnshore wind · 150 MW · in study
- Solar project GEN-2022-076, Stevens CountySolar · 500 MW · withdrawn
- Onshore wind project GEN-2022-059, Stevens CountyOnshore wind · 500 MW · withdrawn
- Onshore wind project GEN-2007-058, Stevens CountyOnshore wind · 202 MW · withdrawn
- Onshore wind project GEN-2007-059, Stevens CountyOnshore wind · 202 MW · withdrawn
- Onshore wind project GEN-2022-202, Stevens CountyOnshore wind · 200 MW · withdrawn
- Solar project GEN-2024-096, Stevens CountySolar · 200 MW · withdrawn
- Onshore wind project GEN-2003-013, Stevens CountyOnshore wind · 198 MW · withdrawn
- Solar project GEN-2022-215, Stevens CountySolar · 154 MW · withdrawn
- Gas project GEN-2009-062, Stevens CountyGas · 115 MW · withdrawn
- Onshore wind project GEN-2002-018, Stevens CountyOnshore wind · 101 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem