ONSHORE WIND · SPPOnshore wind project GEN-2021-021, Stevens County
Onshore wind project GEN-2021-021, Stevens County is a 150 MW onshore wind request in interconnection study in the SPP interconnection queue, in Stevens County, Kansas, connecting to SPS.
Queue statusIn planning
- PlanningQueued Apr 2021 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2021-021
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SPS
- Connection point (POI)
- Carpenter 345 kV Substation
- Location
- Stevens County, Kansas
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Service type
- Energy only (ERIS)
- Study phase
- FACILITY STUDY STAGE
- Queue status
- Active
- Entered queue
- 20 April 2021
- Proposed online date
- December 2027
Location
Marker shows the centre of Stevens County; the queue data does not give exact sites.
Other requests in Stevens County
- Solar + storage project GEN-2020-008, Stevens CountySolar + storage · 250 MW · agreement signed
- Solar project GEN-2024-032, Stevens CountySolar · 250 MW · in study
- Solar project GEN-2022-076, Stevens CountySolar · 500 MW · withdrawn
- Onshore wind project GEN-2022-059, Stevens CountyOnshore wind · 500 MW · withdrawn
- Onshore wind project GEN-2007-058, Stevens CountyOnshore wind · 202 MW · withdrawn
- Onshore wind project GEN-2007-059, Stevens CountyOnshore wind · 202 MW · withdrawn
- Onshore wind project GEN-2022-202, Stevens CountyOnshore wind · 200 MW · withdrawn
- Solar project GEN-2024-096, Stevens CountySolar · 200 MW · withdrawn
- Onshore wind project GEN-2003-013, Stevens CountyOnshore wind · 198 MW · withdrawn
- Solar project GEN-2022-215, Stevens CountySolar · 154 MW · withdrawn
- Gas project GEN-2009-062, Stevens CountyGas · 115 MW · withdrawn
- Onshore wind project GEN-2002-018, Stevens CountyOnshore wind · 101 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem