SOLAR + STORAGE · SPP

Solar + storage project GEN-2024-215, Cloud County

Solar + storage project GEN-2024-215, Cloud County is a 300 MW solar + storage request in interconnection study in the SPP interconnection queue, in Cloud County, Kansas, connecting to ITCGP.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2024-215
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
ITCGP
Connection point (POI)
Elm Creek 345 kV Substation
Location
Cloud County, Kansas
Technology
Solar: 300 MW · Battery
Total requested
300 MW
Service type
NRIS and ERIS
Study phase
DISIS STAGE
Queue status
Active
Entered queue
1 March 2025
Proposed online date
October 2029

Location

Marker shows the centre of Cloud County; the queue data does not give exact sites.

Power plants in Kansas · Transmission lines in Kansas

Other requests in Cloud County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem