🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Kansas

SOLAR · SPP

Solar project GEN-2024-288, Cloud County

Solar project GEN-2024-288, Cloud County is a 130 MW solar request in interconnection study in the SPP interconnection queue, in Cloud County, Kansas, connecting to SUNC.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2024-288
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SUNC
Connection point (POI)
Elm Creek - Tobias 345 kV Line
Location
Cloud County, Kansas
Technology
Solar: 130 MW
Total requested
130 MW
Service type
NRIS and ERIS
Study phase
DISIS STAGE
Queue status
Active
Entered queue
1 March 2025
Proposed online date
October 2030

Location

Marker shows the centre of Cloud County; the queue data does not give exact sites.

Power plants in Kansas · Transmission lines in Kansas

Other requests in Cloud County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem