Gas project ERAS-2025-017, Finney County

Gas project ERAS-2025-017, Finney County is a 600 MW gas request in interconnection study in the SPP interconnection queue, in Finney County, Kansas, connecting to SEPC.

Queue statusIn planning
  1. PlanningQueued Sep 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
ERAS-2025-017
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SEPC
Connection point (POI)
Holcomb 345 kV Substation
Location
Finney County, Kansas
Technology
Gas: 600 MW
Total requested
600 MW
Service type
NRIS and ERIS
Study phase
ERAS
Queue status
Active
Entered queue
24 September 2025
Proposed online date
December 2029

Location

Marker shows the centre of Finney County; the queue data does not give exact sites.